== Typical Building Permit Application Process == | |||
<uml> | |||
title "Generic Building Permit Application Process" | |||
participant "Owner" | |||
participant "Architect\nPrime Consultant" | |||
participant "Sub(M/E/S)\nConsultant" | |||
participant "Geotech\nConsultant" | |||
participant "Building Energy\nConsultant" | |||
participant "Synergy" | |||
participant "City of\nEdmonton" | |||
participant "3rd party\nConsultant" | |||
Note over "Owner","Synergy": Project Award and Permit Applicaiton | |||
"Owner"->"Synergy":Survey Plan | |||
"Architect\nPrime Consultant" -> "Synergy": Architectual Drawing\nSchedule A1, A2, B1, B2 | |||
"Sub(M/E/S)\nConsultant" -> "Synergy": M/E/S Drawing\nSchedule A2, B1, B2 | |||
"Geotech\nConsultant" -> "Synergy": GeoReport\nSchedule A2, B1, B2 | |||
"Building Energy\nConsultant"->"Synergy":Energy Report | |||
"Synergy"->"Owner": Schedule A1, A2s, B1s, B2s | |||
"Owner"->"Synergy": Signed Schedules | |||
"Synergy" ->"City of\nEdmonton": Survey Plan | |||
"Synergy" ->"City of\nEdmonton": Drawings | |||
"Synergy" ->"City of\nEdmonton": Signed Schedules | |||
"Synergy" ->"City of\nEdmonton": Fire Safety Plan | |||
"Synergy" ->"City of\nEdmonton": Filled out\nApplication Form | |||
"City of\nEdmonton" -> "Synergy": Fee Assessment | |||
"Synergy" ->"City of\nEdmonton": Payment | |||
"City of\nEdmonton"->"City of\nEdmonton":Review\nApplication | |||
"City of\nEdmonton"-->"Synergy":Any Information Needed | |||
"Synergy"-->"City of\nEdmonton":Any Information Needed | |||
"City of\nEdmonton"->"Synergy":Building Permit Released | |||
"Synergy"-->"3rd party\nConsultant": Engage 3rd paty Consultant | |||
"3rd party\nConsultant"-->"Synergy": Additional Required Schedules and Drawings | |||
"Synergy"-->"City of\nEdmonton": Additional Required\nSchedules and Drawings | |||
</uml> | |||
For More: you can also check out | |||
* [[Development and Building Permits]] | |||
* [[Demo Permit Process]] | |||
* [[How to: Get Utility - Gas]] | |||
* [[How to: Get Utility - Water]] | |||
* [[Project Close Out Process]] | |||
Latest revision as of 05:45, 22 June 2022
Typical Building Permit Application Process