== Typical Building Permit Application Process ==
+
Here is a general step-by-step procedure to get water for construction projects in Edmonton, Alberta:
  
−
<sequencediagram style="modern">
+
# Determine water service requirements: The first step is to determine the water service requirements for the construction project. This includes the estimated water consumption, the pressure requirements, and the location of the water meter.
−
title "How to Get Utility to Project - Power"
+
# Contact the local water utility provider: In Edmonton, the local water utility provider is EPCOR. Contact them to find out about the requirements for setting up a new water service and to obtain an application form.
 +
# Submit an application for water service: Complete and submit the application form, which will require information on the water service requirements and the location of the construction project. The application will also require payment of any applicable fees.
 +
# Obtain water service permits: Before the water service can be installed, it may be necessary to obtain permits from the local government, such as the City of Edmonton. The permits may require site inspections, fees, and additional documentation.
 +
# Install the water service: Once the permits have been obtained, the water service provider will install the water service at the construction project site. The installation will typically include the water meter, the water piping, and any necessary valves or fittings.
 +
# Schedule a water service inspection: Once the water service has been installed, a water service inspection will be required to ensure that the water service meets all safety and regulatory requirements. The water service provider will typically arrange for the inspection.
 +
# Activate the water service: After the water service has passed the inspection, it can be activated. The water utility provider will typically provide instructions on how to activate the water service and how to read the water meter.
  
−
participant "Electrical\nConsultant"
+
In summary, the process to get water for construction projects in Edmonton involves contacting the local water utility provider, submitting an application for water service, obtaining water service permits, installing the water service, scheduling a water service inspection, and activating the water service. It's important to work closely with the water utility provider and local government to ensure that all requirements and regulations are met.
−
participant "Owner"
 
−
participant "Synergy"
 
−
participant "City of\nEdmonton"
 
−
participant "Electrical\nTrade"
 
−
participant "EPCOR\nPower"
 
−
participant "Retailer"
 
−
 
 
−
"EPCOR\nPower" -> "Electrical\nConsultant" :Engineering and Construction agreement\nService Offer Letter
 
−
Note over "Electrical\nConsultant","Owner" : Sign Offer Letter
 
−
"Electrical\nConsultant" -> "Synergy":  Engineering and Construction\nagreement Service Offer Letter
 
−
"Owner" -> "EPCOR\nPower": Pay Fee
 
−
"Synergy" -> "EPCOR\nPower":EPCOR Commercial Customer\nApplication (permanent)
 
−
"Synergy" --> "EPCOR\nPower":3rd Party Auth. Letter Add to\naccount if App. not submitted
 
−
"Synergy" --> "EPCOR\nPower":EPCOR Commercial Customer\nApplication (temp)
 
−
Note over "Synergy","EPCOR\nPower": Confirm Site ID(s), Address(es)
 
−
"Synergy" -> "Retailer" : Enroll with Retailer using Site ID.
 
−
Note over "City of\nEdmonton","Electrical\nTrade" : Temp Power Permit\nApplied
 
−
Note over "Synergy","Electrical\nTrade" : Transformer Base\nInstallation/Inspection
 
−
Note over "Synergy","Electrical\nTrade" : Main Distribution EQM\nInstallation/Inspection
 
−
Note over "Synergy","Electrical\nTrade" : Temp Service Equipment\nInstallation/Inspection
 
−
"Synergy" -> "EPCOR\nPower" :confirm prerequisite\nconditions completion
 
−
"EPCOR\nPower" -> "Synergy" : Queue: ETA 6 Wks for\nTransformer Installation
 
−
Note over "Synergy","EPCOR\nPower" : Transformer Installation
 
−
"Synergy" -> "EPCOR\nPower" : Apply Power Meter
 
−
"EPCOR\nPower" -> "Synergy" : Queue: ETA 1 WK for Meter
 
−
Note over "Synergy","EPCOR\nPower" : Power Meter Installation
 
−
"Retailer" -> "Synergy" : Site Energized
 
−
</sequencediagram>
 
−
 
 
−
For More: you can also check out
 
−
* [[Development and Building Permits]]
 
−
* [[Demo Permit Process]]
 
−
* [[How to: Get Utility - Gas]]
 
−
* [[How to: Get Utility - Water]]
 
−
* [[Project Close Out Process]]
 

Latest revision as of 23:37, 20 February 2023

Here is a general step-by-step procedure to get water for construction projects in Edmonton, Alberta:

  1. Determine water service requirements: The first step is to determine the water service requirements for the construction project. This includes the estimated water consumption, the pressure requirements, and the location of the water meter.
  2. Contact the local water utility provider: In Edmonton, the local water utility provider is EPCOR. Contact them to find out about the requirements for setting up a new water service and to obtain an application form.
  3. Submit an application for water service: Complete and submit the application form, which will require information on the water service requirements and the location of the construction project. The application will also require payment of any applicable fees.
  4. Obtain water service permits: Before the water service can be installed, it may be necessary to obtain permits from the local government, such as the City of Edmonton. The permits may require site inspections, fees, and additional documentation.
  5. Install the water service: Once the permits have been obtained, the water service provider will install the water service at the construction project site. The installation will typically include the water meter, the water piping, and any necessary valves or fittings.
  6. Schedule a water service inspection: Once the water service has been installed, a water service inspection will be required to ensure that the water service meets all safety and regulatory requirements. The water service provider will typically arrange for the inspection.
  7. Activate the water service: After the water service has passed the inspection, it can be activated. The water utility provider will typically provide instructions on how to activate the water service and how to read the water meter.

In summary, the process to get water for construction projects in Edmonton involves contacting the local water utility provider, submitting an application for water service, obtaining water service permits, installing the water service, scheduling a water service inspection, and activating the water service. It's important to work closely with the water utility provider and local government to ensure that all requirements and regulations are met.