{| class="wikitable"
+
 
−
| colspan="12" rowspan="2" |SGC Submission Review Procedures
+
[[File:SGS Submission Review Process.png|center|thumb|1428x1428px]]
−
|-
+
 
−
|-
+
 
−
|All  submissions are to be reviews as per the table outlined below
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|-
 
−
|
 
−
|
 
−
|Submissions (New & Existing Projects)
 
−
With Commercial Terms (hard bid, RFP or negotiated)
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|Budget  Submissions (New & Existing Projects)
 
−
Without Commerical Terms
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|-
 
−
|
 
−
|Value in Millions
 
−
|0-1
 
−
|1-5
 
−
|6-15
 
−
|15-30
 
−
|>30
 
−
|0-1
 
−
|1-5
 
−
|6-15
 
−
|15-30
 
−
|>30
 
−
|-
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|-
 
−
| rowspan="6" |Estimate Reviews
 
−
|Lead Estimator
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|-
 
−
|Chief Estimator (or designate)
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√*optional
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|√
 
−
|-
 
−
|Project Lead (Project Development Manager/Construction  manager) - if applicable
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|-
 
−
|Operations Manager
 
−
|
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|-
 
−
|Business Unit President
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|-
 
−
|COO
 
−
|
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|√*optional
 
−
|-
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|-
 
−
| rowspan="6" |Fee Reviews
 
−
|Chief Estimator (or designate)
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|√
 
−
|√
 
−
|√
 
−
|-
 
−
|Project Lead (Project Development Manager/Construction  manager) - if applicable
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|-
 
−
|Operations Manager
 
−
|
 
−
|√
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|√
 
−
|√
 
−
|√
 
−
|-
 
−
|Business Unit President
 
−
|
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|√
 
−
|-
 
−
|COO
 
−
|
 
−
|
 
−
|√* Optional
 
−
|√
 
−
|√
 
−
|
 
−
|
 
−
|
 
−
|√*optional
 
−
|√
 
−
|-
 
−
|SGC President
 
−
|
 
−
|
 
−
|
 
−
|√*Optional
 
−
|√
 
−
|
 
−
|
 
−
|
 
−
|
 
−
|√*optional
 
−
|}
 
 
√*optional    Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review
 
√*optional    Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review
  
 
In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review.
 
In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review.

Latest revision as of 19:47, 19 July 2023

SGS Submission Review Process.png


√*optional Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review

In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review.