[[File:SGS Submission Review Process.png|center|thumb|1428x1428px]] | |||
| | |||
| | |||
| | |||
√*optional Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review | √*optional Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review | ||
In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review. | In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review. | ||
Latest revision as of 19:47, 19 July 2023

√*optional Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review
In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review.