Difference between revisions of "Development and Building Permits"
Jump to navigation
Jump to search
(Created page with "``` ```") |
|||
| (14 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
| − | + | == Typical Building Permit Application Process == | |
| − | + | <uml> | |
| + | title "Generic Building Permit Application Process" | ||
| + | participant "Owner" | ||
| + | |||
| + | participant "Architect\nPrime Consultant" | ||
| + | participant "Sub(M/E/S)\nConsultant" | ||
| + | participant "Geotech\nConsultant" | ||
| + | participant "Building Energy\nConsultant" | ||
| + | participant "Synergy" | ||
| + | participant "City of\nEdmonton" | ||
| + | participant "3rd party\nConsultant" | ||
| + | |||
| + | Note over "Owner","Synergy": Project Award and Permit Applicaiton | ||
| + | "Owner"->"Synergy":Survey Plan | ||
| + | "Architect\nPrime Consultant" -> "Synergy": Architectual Drawing\nSchedule A1, A2, B1, B2 | ||
| + | "Sub(M/E/S)\nConsultant" -> "Synergy": M/E/S Drawing\nSchedule A2, B1, B2 | ||
| + | "Geotech\nConsultant" -> "Synergy": GeoReport\nSchedule A2, B1, B2 | ||
| + | "Building Energy\nConsultant"->"Synergy":Energy Report | ||
| + | "Synergy"->"Owner": Schedule A1, A2s, B1s, B2s | ||
| + | "Owner"->"Synergy": Signed Schedules | ||
| + | "Synergy" ->"City of\nEdmonton": Survey Plan | ||
| + | "Synergy" ->"City of\nEdmonton": Drawings | ||
| + | "Synergy" ->"City of\nEdmonton": Signed Schedules | ||
| + | "Synergy" ->"City of\nEdmonton": Fire Safety Plan | ||
| + | "Synergy" ->"City of\nEdmonton": Filled out\nApplication Form | ||
| + | "City of\nEdmonton" -> "Synergy": Fee Assessment | ||
| + | "Synergy" ->"City of\nEdmonton": Payment | ||
| + | "City of\nEdmonton"->"City of\nEdmonton":Review\nApplication | ||
| + | "City of\nEdmonton"-->"Synergy":Any Information Needed | ||
| + | "Synergy"-->"City of\nEdmonton":Any Information Needed | ||
| + | "City of\nEdmonton"->"Synergy":Building Permit Released | ||
| + | "Synergy"-->"3rd party\nConsultant": Engage 3rd paty Consultant | ||
| + | "3rd party\nConsultant"-->"Synergy": Additional Required Schedules and Drawings | ||
| + | "Synergy"-->"City of\nEdmonton": Additional Required\nSchedules and Drawings | ||
| + | </uml> | ||
| + | |||
| + | For More: you can also check out | ||
| + | * [[Development and Building Permits]] | ||
| + | * [[Demo Permit Process]] | ||
| + | * [[How to: Get Utility - Gas]] | ||
| + | * [[How to: Get Utility - Water]] | ||
| + | * [[Project Close Out Process]] | ||
Latest revision as of 05:45, 22 June 2022
Typical Building Permit Application Process
For More: you can also check out