Difference between revisions of "Project Change Management"
Jump to navigation
Jump to search
| Line 3: | Line 3: | ||
'''Consultant Issued Change Notices:''' | '''Consultant Issued Change Notices:''' | ||
| − | A consultant issued change notice is typically issued to request pricing from a General Contractor for the change of a project's scope of work . This can either be a ''credit'' or an ''extra''. | + | A consultant issued change notice is typically issued by the Prime Consultant to request pricing from a General Contractor for the change of a project's scope of work . This can either be a ''credit'' or an ''extra''. |
Terminology examples of this are: | Terminology examples of this are: | ||
PCN (Proposed Change Notice), | PCN (Proposed Change Notice), | ||
CCN (Contemplated Change Notice) | CCN (Contemplated Change Notice) | ||
Revision as of 23:01, 11 May 2020
Change Order Information
Consultant Issued Change Notices:
A consultant issued change notice is typically issued by the Prime Consultant to request pricing from a General Contractor for the change of a project's scope of work . This can either be a credit or an extra.
Terminology examples of this are: PCN (Proposed Change Notice), CCN (Contemplated Change Notice)