Project Close Out
Objective:
The intent is to give a good idea of project close out requirements to ensure clean and successful project close out. The requirements might vary from Jurisdictions.
Project Close Out:
Are you only looking for a simple and quick guide for close out procedures? Take a look here: Project Close Out Process
Close out Schedule
When project is close enough to the end, to help better tracking items, the project team can generate a close out schedule, which is a more extended version of the "xx weeks look ahead". This schedule should be seperated by Trades/Area/Phases, and as granular as logic allows. This schedule should be tracked and compared daily to ensure items are being completed or closed out as planned.