SGC Submission Review Procedures

From SynWiki
Revision as of 19:43, 19 July 2023 by Carsen der (talk | contribs)
Jump to navigation Jump to search


SGC Submission Review Procedures
All submissions are to be reviews as per the table outlined below
Submissions (New & Existing Projects)

With Commercial Terms (hard bid, RFP or negotiated)

Budget Submissions (New & Existing Projects)

Without Commerical Terms

Value in Millions 0-1 1-5 6-15 15-30 >30 0-1 1-5 6-15 15-30 >30
Estimate Reviews Lead Estimator √ √ √ √ √ √ √ √ √ √
Chief Estimator (or designate) √*optional √ √ √ √ √*optional √*optional √ √ √
Project Lead (Project Development Manager/Construction manager) - if applicable √ √ √ √ √ √ √ √ √
Operations Manager √*optional √ √ √ √*optional √ √
Business Unit President √*optional √ √ √*optional √
COO √*optional √ √*optional
Fee Reviews Chief Estimator (or designate) √ √ √ √ √ √ √ √
Project Lead (Project Development Manager/Construction manager) - if applicable √ √ √ √ √ √ √ √ √
Operations Manager √ √ √ √ √ √ √
Business Unit President √*optional √ √ √ √*optional √ √
COO √* Optional √ √ √*optional √
SGC President √*Optional √ √*optional


√*optional Denotes that this individual is to be made aware of any submisison (through MMM, direct contact, etc) and will decide on what level of review is required and who is to be included in the review

In any instance, the chief estimator or designate is to properly inform the optional persons of the project and determine the level of review.